May 3, 2011 DONE Space evaluation team appointed; visit 3 facilities later.
June 1, 2011 DONE Hospitality and connections leader identified.
June 5, 2011 DONE Day of Prayer, Repentance and Healing scheduled.
June 5, 2011 DONE Three-person team in place to plan and market new contemporary service.
June 15, 2011 DONE Space evaluation team has written recommendations to church council for changes.(Date changed by coach.)
June 20, 2011 DONE Day of visioning scheduled 6-9 p.m.
July 1, 2011 DONE Director of contemporary music hired.
August 14, 2011 DONE Part-time children and youth coordinator hired.
August 31, 2011 DONE Hospitality and connections leader has built team and shares/trains team.
September 4, 2011 DONE Contemporary worship service in place.
September 19, 2011  DONE Church Council has approved new Vision Statement.
November 15, 2011 DONE Finance committee has reviewed all church programs to determine if they match the church mission; has reviewed budget spending and stewardship plan for 2012 is in place.
December 3, 2011 DONE Day long goal setting session for 2012 with church council has occurred.
Spring, 2012 All church signage needs are corrected and in place (indoor and outdoor)
Spring 2012
Community open house to celebrate program renovations.

 

 

 

 

 

 

 

St. Paul UMC Timelines for Healthy ChurchInitiative

 

May 3DONE

Space evaluation team appointed; visit 3 facilities later.(Date changed by coach)

June 1DONE

Hospitality and connections leader identified.

June 5DONE

Day of Prayer, Repentance and Healing scheduled. (Date changed by coach.)

June 5DONE

Three-person team in place to plan and market new contemporary service.

June 15DONE

Space evaluation team has written recommendations to church council for changes.(Date changed by coach.)

June 20DONE

Day of visioning scheduled 6-9 p.m.

July 1

Director of contemporary music hired.

July 30

Congregation has approved new Vision Statement.

August 1

Hospitality and connections leader has built team and shares/trains team.

August 14

Part-time children and youth coordinator hired.

September 1

Contemporary worship service in place.

September 11

Community open house to celebrate program renovations.

October 1

Day long goal setting session for 2012 with church council has occurred.

October 1

Finance committee has reviewed all church programs to determine if they match the church mission; has reviewed budget spending and stewardship plan for 2012 is in place.

December 31